ANALISA PENYEBAB DAN AKIBAT PERUBAHAN KONTRAK PEKERJAAN (CONTRACT CHANGE ORDER) TERHADAP BIAYA PADA PROYEK TRANSMISI

Main Article Content

Diah Margareta
Ani Firda
Yasmid Yasmid

Abstract

Thisresearch was motivated by a lot of demands of contract change order addendum in the related
agency. From this research, researcher was expected to be able to describe the elements of main cause of
contract change order and impact on the contract cost. The method used in this research wasStatistics
Descriptive for describing the questionnaire results, whereas the calculation of the new value of contractwas
using the unit price calculation analysis. Sources of data in this research were 8 people consisting of project
owners and contractor. Basedon the results of the main causes of contract change order, it was found that the
main cause of contract change order was the location change of the project resulting from transmission lines
through the region of coal mining, the main party that influenced the contract change order was the owner of
the project, The implementation phase of contract change order was mid-contract work, the stages leading to
contract change order was land acquisition and the impact of contract change order in the cost was the
decrease of contract value from the initial contract.